Snackbrands

Heat Exchange Bund

PROJECT Install new flooring on bund and around machinery
WHAT WE DID Remove all existing flooring, install new flooring in and around machinery
CLIENT Snackbrands: https://www.snackbrands.com.au/
TIMELINE Approximately 12 hours. The project was completed along with other major areas in the facility at the same time. 

PROJECT INFORMATION

The client was after a non-slip floor, in bright colours in order to indicate the hazardous area. The machinery was clearly a challenge to get around however our Western Sydney team knew the challenge they were in for and worked hard on this project to complete it to the highest standard possible. 

The red and yellow lines around the outside of the bund clearly indicate the hazardous area to those working around it. 

snackbrands1

CHALLENGES

  • Minimal room to get around machinery
  • Tight time-frame
  • Colours to match the previous flooring works by Allied Finishes
  • Other major areas had to be completed at the same time
  • Shut-downs are very rare so this had to be completed during a tight weekend

RESULTS

The client was very satisfied with the overall result. The new flooring has meant that there have been no slips, trips or falls in the area at all since the time of completion. 